Plan Review Timelines

Plan Review Timelines

Building

First Review Timeframe Goals
Commercial: 21 days
Commercial Minor: 14 days
Commercial 7 Day: 7 days
Standard Plan: 21 days
Custom Single Family Residence: 21 days
Residential Minor: 14 days
Revisions: 10 days
Phased Projects: 42 days
Correction / All subsequent reviews: 10 days

NOTE:


Review Timeframe Goals Annual Operational
All Permits: 10 days or 20 days

Review Timeframe Goals Temporary Operational
Exhibit and Trade Show & Membrane Building Structure, tent or canopy (Range 1 or 2): Immediate, 3 days, 5 days, 10 days
Exhibit and Trade Show & Membrane Building Structure, tent or canopy (Range 3 or 4): Immediate, 3 days, 10 days, 20 days
All Other Permits: 10 days or 20 days